NTB REMODEL

First Floor Work

< BACK TO PICTURE GALLERY | 1 | 2 | BACK TO NTB GALLERY >
 
Due to the size and number of photographs
this page will take 1-2 minutes to load
We appreciate your patience.
 
10-24-00_From_Front_Door

October 24 - View from the front entrance.  
Behind this wall is the old garage which is being 
converted into the new computer room.

 
10-25-00_1st_Floor_SE_Room

October 25 - Southeast room.  Window blocked in.

 
10-31-00_1st_Floor_South_Room

October 31 - South room.  
Preparatory work for construction of walls.

 
11-1-00_1st_Floor_South_Room

November 1 - South room.  
Frame work for walls begun.  
In front of the walls you can see where the cistern has been removed.  

To see pictures of the removal of the cistern click here

 
11-2-00_1st_Floor_South_Room

November 2 - South rooms.  
Frame work for wall dividing the space into two rooms begun.

 
11-3-00_1st_Floor_South_Room

November 3

 
11-5-00_1st_Floor_South_Room

November 5 - South rooms.  
Drywall is brought in.

 
11-5-00_1st_Floor_South_Room

November 5

 
11-5-00_1st_Floor_South_Room

November 5 - View of south rooms and doorway 
on the right is a hallway which leads to 
a small bathroom and the old garage.

 
11-13-00_1st_Floor_South_East_Room

November 13 - Window work on south rooms begins.

 
11-13-00_1st_Floor_South_West_Room

November 13 - Close-up of doorways for south rooms.

 
11-30-00_tiling

November 30 - Tiling work begins.

 
11-30-00_tiling

November 30

 
11-30-00_interior_walls

November 30 - Front door.

 
12-11-00_1st_floor_stairs

December 11 - View from front entrance.  
Tiling work finished.

 
12-11-00_stairs

December 11 - View from top of stairs.

 